Avalon/Brazos Landing/Commonwealth Drainage Impr- Phase I

View all

Project

Description:

Reconstruct the existing weir at the FBC LID No. 14 outfall structure to increase the outfall and pumping efficiency while maintaining the existing lake elevation. The project will also reduce the tailwater elevation of the lake to provide additional capacity for stormwater drainage during major storm events.

The 2017 Drainage Study identified improvements necessary to the downstream weir at the FBC LID No. 14 outfall structure that will reduce the overall street ponding along Elkins and Commonwealth Boulevards.